About the project
FYCO took on the responsibility of supporting a major carrier in its goal of expanding bandwidth capacity in five
cities in Mexico: Querétaro, Mexico City, Tijuana, Monterrey and Mazatlán.
This task, in addition to providing materials, involved the planning of 5 new nodes, where tasks such as the
selection and placement of equipment in racks, activation of FOSS panels and installation of FED, as well as the
deployment of fiber within different areas in the data centers were considered.
The challenge
Mexico is a country with sustained growth in telecommunications networks. The carrier required a versatile partner that could manage a trained and efficient work team. To allow the reliable operation of the nodes, FYCO had to evaluate the conditions of the site, taking into account architectural principles in the data centers to select the best location and infrastructure, implementing security measures and data management.

“Mexico is a very large country, and being able to move around different cities, providing quality service and
personalized, close and open attention to the client, was our added value. We entered a very competitive area,
and this challenge ended up being a great success.”
FYCO Mexico Team
The strategy
- Close relationship
Open and direct communication between both parties facilitated accurate answers and timely solutions, establishing a fluid and close relationship.
- Specialized attention
Appointing a specialist engineer to head the project allowed us to understand the needs and provide continuity to more and more activities with the support of several areas and numerous FYCO collaborators.
- Continuous follow-up
Daily reports and monthly meetings ensuredtransparency and clarity in the actions. At the end of each day, the team documented the activities carried out during the day and shared it with the company. Sessions were also held for a detailed review of all files and photographic evidence of the work.
“From planning the new nodes to installing the equipment, each step was carefully executed by our highly skilled team. This project not only represented a technical challenge, but also an opportunity to demonstrate our commitment to innovation and excellence.”
FYCO Mexico Team
Figures
- 100% of the FYCO Mexico team involved.
- 5 new nodes built in different cities in Mexico.
- 64 FEDs installed on each node.
- 20 thousand users benefited from each FED.
- 2 years as estimated duration to complete the project.
Results
- Project Growth
This company saw in FYCO a responsible service provider to start growing in Mexico. As a result, initiatives were added in the data centers of three new locations in the country, Saltillo, León and
Aguascalientes.
- Technological development
With the construction of 5 nodes, the company strengthened its Carrier function by expanding its service coverage in a more efficient way and with updated equipment, achieving a much higher data transmission through its communication networks.
- Operational Agility
Response and execution times were optimized, going from two days to five days respectively, allowing for
faster and more efficient progress in the different phases of the project.